Following a significant change to a business process, a risk practitioner believes the associated risk has been reduced. The risk practitioner should advise the risk owner to FIRST
A.
review the key risk indicators.
B.
conduct a risk analysis.
C.
update the risk register
D.
reallocate risk response resources.