After identifying new risk events during a project, the project manager s NEXT step should be to:

A.
determine if the scenarios need 10 be accepted or responded to.
Answers
A.
determine if the scenarios need 10 be accepted or responded to.
B.
record the scenarios into the risk register.
Answers
B.
record the scenarios into the risk register.
C.
continue with a qualitative risk analysis.
Answers
C.
continue with a qualitative risk analysis.
D.
continue with a quantitative risk analysis.
Answers
D.
continue with a quantitative risk analysis.
Suggested answer: B