Question 290 - CRISC discussion
After identifying new risk events during a project, the project manager s NEXT step should be to:
A.
determine if the scenarios need 10 be accepted or responded to.
B.
record the scenarios into the risk register.
C.
continue with a qualitative risk analysis.
D.
continue with a quantitative risk analysis.