Question 303 - CRISC discussion
Which of the following is MOST critical to the design of relevant risk scenarios?
A.
The scenarios are based on past incidents.
B.
The scenarios are linked to probable organizational situations.
C.
The scenarios are mapped to incident management capabilities.
D.
The scenarios are aligned with risk management capabilities.