Question 370 - CRISC discussion
Due to a change in business processes, an identified risk scenario no longer requires mitigation. Which of the following is the MOST important reason the risk should remain in the risk register?
A.
To support regulatory requirements
B.
To prevent the risk scenario in the current environment
C.
To monitor for potential changes to the risk scenario
D.
To track historical risk assessment results