List of questions
Related questions
Question 389 - CRISC discussion
What should be the PRIMARY objective for a risk practitioner performing a post-implementation review of an IT risk mitigation project?
A.
Documenting project lessons learned
B.
Validating the risk mitigation project has been completed
C.
Confirming that the project budget was not exceeded
D.
Verifying that the risk level has been lowered
Your answer:
0 comments
Sorted by
Leave a comment first