What should be the PRIMARY objective for a risk practitioner performing a post-implementation review of an IT risk mitigation project?

A.
Documenting project lessons learned
Answers
A.
Documenting project lessons learned
B.
Validating the risk mitigation project has been completed
Answers
B.
Validating the risk mitigation project has been completed
C.
Confirming that the project budget was not exceeded
Answers
C.
Confirming that the project budget was not exceeded
D.
Verifying that the risk level has been lowered
Answers
D.
Verifying that the risk level has been lowered
Suggested answer: D