An organization has just implemented changes to close an identified vulnerability that impacted a critical business process. What should be the NEXT course of action?
A.
Redesign the heat map.
B.
Review the risk tolerance.
C.
Perform a business impact analysis (BIA)
D.
Update the risk register.