Which of the following is the MOST important objective of regularly presenting the project risk register to the project steering committee?

A.
To allocate budget for resolution of risk issues
Answers
A.
To allocate budget for resolution of risk issues
B.
To determine if new risk scenarios have been identified
Answers
B.
To determine if new risk scenarios have been identified
C.
To ensure the project timeline is on target
Answers
C.
To ensure the project timeline is on target
D.
To track the status of risk mitigation actions
Answers
D.
To track the status of risk mitigation actions
Suggested answer: D