Which of the following is the MOST important reason to revisit a previously accepted risk?

A.
To update risk ownership
Answers
A.
To update risk ownership
B.
To review the risk acceptance with new stakeholders
Answers
B.
To review the risk acceptance with new stakeholders
C.
To ensure risk levels have not changed
Answers
C.
To ensure risk levels have not changed
D.
To ensure controls are still operating effectively
Answers
D.
To ensure controls are still operating effectively
Suggested answer: C