Which of the following is the MOST important objective of embedding risk management practices into the initiation phase of the project management life cycle?

A.
To deliver projects on time and on budget
Answers
A.
To deliver projects on time and on budget
B.
To assess inherent risk
Answers
B.
To assess inherent risk
C.
To include project risk in the enterprise-wide IT risk profit.
Answers
C.
To include project risk in the enterprise-wide IT risk profit.
D.
To assess risk throughout the project
Answers
D.
To assess risk throughout the project
Suggested answer: B