Question 553 - CRISC discussion
Which of the following criteria associated with key risk indicators (KRIs) BEST enables effective risk monitoring?
A.
Approval by senior management
B.
Low cost of development and maintenance
C.
Sensitivity to changes in risk levels
D.
Use of industry risk data sources
Your answer: