Which of the following is the PRIMARY reason to have the risk management process reviewed by a third party?

A.
Obtain objective assessment of the control environment.
Answers
A.
Obtain objective assessment of the control environment.
B.
Ensure the risk profile is defined and communicated.
Answers
B.
Ensure the risk profile is defined and communicated.
C.
Validate the threat management process.
Answers
C.
Validate the threat management process.
D.
Obtain an objective view of process gaps and systemic errors.
Answers
D.
Obtain an objective view of process gaps and systemic errors.
Suggested answer: A