Which of the following risk management practices BEST facilitates the incorporation of IT risk scenarios into the enterprise-wide risk register?

A.
Key risk indicators (KRls) are developed for key IT risk scenarios
Answers
A.
Key risk indicators (KRls) are developed for key IT risk scenarios
B.
IT risk scenarios are assessed by the enterprise risk management team
Answers
B.
IT risk scenarios are assessed by the enterprise risk management team
C.
Risk appetites for IT risk scenarios are approved by key business stakeholders.
Answers
C.
Risk appetites for IT risk scenarios are approved by key business stakeholders.
D.
IT risk scenarios are developed in the context of organizational objectives.
Answers
D.
IT risk scenarios are developed in the context of organizational objectives.
Suggested answer: D