While reviewing an organization's monthly change management metrics, a risk practitioner notes that the number of emergency changes has increased substantially Which of the following would be the BEST approach for the risk practitioner to take?

A.
Temporarily suspend emergency changes.
Answers
A.
Temporarily suspend emergency changes.
B.
Document the control deficiency in the risk register.
Answers
B.
Document the control deficiency in the risk register.
C.
Conduct a root cause analysis.
Answers
C.
Conduct a root cause analysis.
D.
Continue monitoring change management metrics.
Answers
D.
Continue monitoring change management metrics.
Suggested answer: C