Question 667 - CRISC discussion
An application runs a scheduled job that compiles financial data from multiple business systems and updates the financial reporting system. If this job runs too long, it can delay financial reporting. Which of the following is the risk practitioner's BEST recommendation?
A.
Implement database activity and capacity monitoring.
B.
Ensure the business is aware of the risk.
C.
Ensure the enterprise has a process to detect such situations.
D.
Consider providing additional system resources to this job.