A deficient control has been identified which could result in great harm to an organization should a low frequency threat event occur. When communicating the associated risk to senior management the risk practitioner should explain:

A.
mitigation plans for threat events should be prepared in the current planning period.
Answers
A.
mitigation plans for threat events should be prepared in the current planning period.
B.
this risk scenario is equivalent to more frequent but lower impact risk scenarios.
Answers
B.
this risk scenario is equivalent to more frequent but lower impact risk scenarios.
C.
the current level of risk is within tolerance.
Answers
C.
the current level of risk is within tolerance.
D.
an increase in threat events could cause a loss sooner than anticipated.
Answers
D.
an increase in threat events could cause a loss sooner than anticipated.
Suggested answer: A