A risk practitioner has received an updated enterprise risk management (ERM) report showing that residual risk is now within the organization's defined appetite and tolerance levels. Which of the following is the risk practitioner's BEST course of action?
A.
Identify new risk entries to include in ERM.
B.
Remove the risk entries from the ERM register.
C.
Re-perform the risk assessment to confirm results.
D.
Verify the adequacy of risk monitoring plans.