Question 717 - CRISC discussion
Which of the following presents the GREATEST risk to change control in business application development over the complete life cycle?
A.
Emphasis on multiple application testing cycles
B.
Lack of an integrated development environment (IDE) tool
C.
Introduction of requirements that have not been approved
D.
Bypassing quality requirements before go-live