An organization has initiated a project to launch an IT-based service to customers and take advantage of being the first to market. Which of the following should be of GREATEST concern to senior management?

A.
More time has been allotted for testing.
Answers
A.
More time has been allotted for testing.
B.
The project is likely to deliver the product late.
Answers
B.
The project is likely to deliver the product late.
C.
A new project manager is handling the project.
Answers
C.
A new project manager is handling the project.
D.
The cost of the project will exceed the allotted budget.
Answers
D.
The cost of the project will exceed the allotted budget.
Suggested answer: B