When reviewing a report on the performance of control processes, it is MOST important to verify whether the:

A.
business process objectives have been met.
Answers
A.
business process objectives have been met.
B.
control adheres to regulatory standards.
Answers
B.
control adheres to regulatory standards.
C.
residual risk objectives have been achieved.
Answers
C.
residual risk objectives have been achieved.
D.
control process is designed effectively.
Answers
D.
control process is designed effectively.
Suggested answer: D