Key risk indicators (KRIs) are MOST useful during which of the following risk management phases?

A.
Monitoring
Answers
A.
Monitoring
B.
Analysis
Answers
B.
Analysis
C.
Identification
Answers
C.
Identification
D.
Response selection
Answers
D.
Response selection
Suggested answer: A