Question 787 - CRISC discussion
The PRIMARY reason for tracking the status of risk mitigation plans is to ensure:
A.
the proposed controls are implemented as scheduled.
B.
security controls are tested prior to implementation.
C.
compliance with corporate policies.
D.
the risk response strategy has been decided.