The PRIMARY reason for tracking the status of risk mitigation plans is to ensure:

A.
the proposed controls are implemented as scheduled.
Answers
A.
the proposed controls are implemented as scheduled.
B.
security controls are tested prior to implementation.
Answers
B.
security controls are tested prior to implementation.
C.
compliance with corporate policies.
Answers
C.
compliance with corporate policies.
D.
the risk response strategy has been decided.
Answers
D.
the risk response strategy has been decided.
Suggested answer: A