For a large software development project, risk assessments are MOST effective when performed:

A.
before system development begins.
Answers
A.
before system development begins.
B.
at system development.
Answers
B.
at system development.
C.
at each stage of the system development life cycle (SDLC).
Answers
C.
at each stage of the system development life cycle (SDLC).
D.
during the development of the business case.
Answers
D.
during the development of the business case.
Suggested answer: C