Question 896 - CRISC discussion
Which of the following is the BEST way to help ensure risk will be managed properly after a business process has been re-engineered?
A.
Reassessing control effectiveness of the process
B.
Conducting a post-implementation review to determine lessons learned
C.
Reporting key performance indicators (KPIs) for core processes
D.
Establishing escalation procedures for anomaly events