List of questions
Related questions
Question 898 - CRISC discussion
When reviewing the business continuity plan (BCP) of an online sales order system, a risk practitioner notices that the recovery time objective (RTO) has a shorter lime than what is defined in the disaster recovery plan (DRP). Which of the following is the BEST way for the risk practitioner to address this concern?
A.
Adopt the RTO defined in the BCR
B.
Update the risk register to reflect the discrepancy.
C.
Adopt the RTO defined in the DRP.
D.
Communicate the discrepancy to the DR manager for follow-up.
Your answer:
0 comments
Sorted by
Leave a comment first