Which of the following should be of MOST concern to a risk practitioner reviewing an organization risk register after the completion of a series of risk assessments?

A.
Several risk action plans have missed target completion dates.
Answers
A.
Several risk action plans have missed target completion dates.
B.
Senior management has accepted more risk than usual.
Answers
B.
Senior management has accepted more risk than usual.
C.
Risk associated with many assets is only expressed in qualitative terms.
Answers
C.
Risk associated with many assets is only expressed in qualitative terms.
D.
Many risk scenarios are owned by the same senior manager.
Answers
D.
Many risk scenarios are owned by the same senior manager.
Suggested answer: A