Question 1017 - CRISC discussion
Which of the following is the MOST important concern when assigning multiple risk owners for an identified risk?
A.
Accountability may not be clearly defined.
B.
Risk ratings may be inconsistently applied.
C.
Different risk taxonomies may be used.
D.
Mitigation efforts may be duplicated.
Your answer: