Which of the following is the MOST important reason to validate that risk responses have been executed as outlined in the risk response plan''
A.
To ensure completion of the risk assessment cycle
B.
To ensure controls arc operating effectively
C.
To ensure residual risk Is at an acceptable level
D.
To ensure control costs do not exceed benefits