A risk practitioner implemented a process to notify management of emergency changes that may not be approved. Which of the following is the BEST way to provide this information to management?

A.
Change logs
Answers
A.
Change logs
B.
Change management meeting minutes
Answers
B.
Change management meeting minutes
C.
Key control indicators (KCIs)
Answers
C.
Key control indicators (KCIs)
D.
Key risk indicators (KRIs)
Answers
D.
Key risk indicators (KRIs)