Question 1094 - CRISC discussion
Which of the following would be of MOST concern to a risk practitioner reviewing risk action plans for documented IT risk scenarios?
A.
Individuals outside IT are managing action plans for the risk scenarios.
B.
Target dates for completion are missing from some action plans.
C.
Senior management approved multiple changes to several action plans.
D.
Many action plans were discontinued after senior management accepted the risk.
Your answer: