Question 1143 - CRISC discussion

Report
Export

Which of the following is the BEST key performance indicator (KPI) to measure how effectively risk management practices are embedded in the project management office (PMO)?

A.
Percentage of projects with key risk accepted by the project steering committee
Answers
A.
Percentage of projects with key risk accepted by the project steering committee
B.
Reduction in risk policy noncompliance findings
Answers
B.
Reduction in risk policy noncompliance findings
C.
Percentage of projects with developed controls on scope creep
Answers
C.
Percentage of projects with developed controls on scope creep
D.
Reduction in audits involving external risk consultants
Answers
D.
Reduction in audits involving external risk consultants
Suggested answer: C