The MOST important measure of the effectiveness of risk management in project implementation is the percentage of projects:

A.
introduced into production without high-risk issues.
Answers
A.
introduced into production without high-risk issues.
B.
having the risk register updated regularly.
Answers
B.
having the risk register updated regularly.
C.
having key risk indicators (KRIs) established to measure risk.
Answers
C.
having key risk indicators (KRIs) established to measure risk.
D.
having an action plan to remediate overdue issues.
Answers
D.
having an action plan to remediate overdue issues.
Suggested answer: A