Question 1163 - CRISC discussion
When implementing an IT risk management program, which of the following is the BEST time to evaluate current control effectiveness?
A.
Before defining a framework
B.
During the risk assessment
C.
When evaluating risk response
D.
When updating the risk register
Your answer: