Which of the following is MOST useful for measuring the existing risk management process against a desired state?

A.
Balanced scorecard
Answers
A.
Balanced scorecard
B.
Risk management framework
Answers
B.
Risk management framework
C.
Capability maturity model
Answers
C.
Capability maturity model
D.
Risk scenario analysis
Answers
D.
Risk scenario analysis
Suggested answer: C