List of questions
Related questions
Question 43 - CAP discussion
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
A.
Avoidance
B.
Mitigation
C.
Exploit
D.
Transference
Your answer:
0 comments
Sorted by
Leave a comment first