ExamGecko
Home Home / ISC / CAP
Question list
Search
Search

List of questions

Search

Related questions











Question 55 - CAP discussion

Report
Export

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

A.
1.06
Answers
A.
1.06
B.
0.92
Answers
B.
0.92
C.
-$37,800
Answers
C.
-$37,800
D.
0.93
Answers
D.
0.93
Suggested answer: B
asked 18/09/2024
Maher Khamessi
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first