Jenny is the project manager of the NHJ Project for her company. She has identified several positive risk events within the project and she thinks these events can save the project time and money. You, a new team member wants to know that how many risk responses are available for a positive risk event. What will

Jenny reply to you?

A.
Four
Answers
A.
Four
B.
Seven
Answers
B.
Seven
C.
Acceptance is the only risk response for positive risk events.
Answers
C.
Acceptance is the only risk response for positive risk events.
D.
Three
Answers
D.
Three
Suggested answer: A