You are the project manager for the NHH project. You are working with your project team to examine the project from four different defined perspectives to increase the breadth of identified risks by including internally generated risks. What risk identification approach are you using in this example?
A.
SWOT analysis
B.
Root cause analysis
C.
Assumptions analysis
D.
Influence diagramming techniques