List of questions
Related questions
Question 70 - CAP discussion
Which one of the following is the only output for the qualitative risk analysis process?
A.
Project management plan
B.
Risk register updates
C.
Enterprise environmental factors
D.
Organizational process assets
Your answer:
0 comments
Sorted by
Leave a comment first