Question 75 - CAP discussion

Report
Export

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?

A.
Seven
Answers
A.
Seven
B.
Three
Answers
B.
Three
C.
Four
Answers
C.
Four
D.
One
Answers
D.
One
Suggested answer: C