What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

A.
Configuration Management System
Answers
A.
Configuration Management System
B.
Project Management Information System
Answers
B.
Project Management Information System
C.
Scope Verification
Answers
C.
Scope Verification
D.
Integrated Change Control
Answers
D.
Integrated Change Control
Suggested answer: A