Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

A.
Risks
Answers
A.
Risks
B.
Costs
Answers
B.
Costs
C.
Resources
Answers
C.
Resources
D.
Communication
Answers
D.
Communication
Suggested answer: A