List of questions
Related questions
Question 115 - CAP discussion
Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?
A.
Mary will utilize the schedule controls and the nature of the schedule for the quantitative analysis of the schedule.
B.
Mary will schedule when the identified risks are likely to happen and affect the project schedule.
C.
Mary will utilize the schedule controls to determine how risks may be allowed to change the project schedule.
D.
Mary will use the schedule management plan to schedule the risk identification meetings throughout the remaining project.
Your answer:
0 comments
Sorted by
Leave a comment first