Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?

A.
Acceptance
Answers
A.
Acceptance
B.
Mitigation
Answers
B.
Mitigation
C.
Avoidance
Answers
C.
Avoidance
D.
Transference
Answers
D.
Transference
Suggested answer: C