Question 127 - CAP discussion
Which of the following documents is described in the statement below?
"It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."
A.
Risk register
B.
Risk management plan
C.
Project charter
D.
Quality management plan