ExamGecko
Home Home / ISC / CAP
Question list
Search
Search

List of questions

Search

Related questions











Question 129 - CAP discussion

Report
Export

Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?

A.
External risk response
Answers
A.
External risk response
B.
Internal risk management strategy
Answers
B.
Internal risk management strategy
C.
Contingent response strategy
Answers
C.
Contingent response strategy
D.
Expert judgment
Answers
D.
Expert judgment
Suggested answer: C
asked 18/09/2024
Instel SL
28 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first