You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

A.
Risk register
Answers
A.
Risk register
B.
Risk log
Answers
B.
Risk log
C.
Risk management plan
Answers
C.
Risk management plan
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: A