Question 178 - CAP discussion
Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?
A.
SV=EV-PV
B.
SV=EV/AC
C.
SV=PV-EV
D.
SV=EV/PV