List of questions
Related questions
Question 184 - CAP discussion
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?
A.
Lessons learned
B.
Scope statement
C.
Risk Breakdown Structure
D.
Technical documentation
Your answer:
0 comments
Sorted by
Leave a comment first