You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

A.
Human resource needs
Answers
A.
Human resource needs
B.
Risks
Answers
B.
Risks
C.
Costs
Answers
C.
Costs
D.
Quality control concerns
Answers
D.
Quality control concerns
Suggested answer: B