Rob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed - even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?

A.
Transference
Answers
A.
Transference
B.
Mitigation
Answers
B.
Mitigation
C.
Enhance
Answers
C.
Enhance
D.
Acceptance
Answers
D.
Acceptance
Suggested answer: D